Evaluating Commitments in the Cost Element Report 
Usage
You switch to a different session and call up the cost element report.
Procedure
Calling up the cost element report
Menu Path |
Logistics ® Project System ® Information System ® Controlling ® Execute Report ® Cost Element Report |
Transaction Code |
GR55 |
Field |
Data |
Project |
T-10### |
Controlling area |
1000 |
Plan version |
0 |
From fiscal year |
Current year |
To fiscal year |
Current year + 2 |
From period |
1 |
To period |
12 |
Additional selection criteria |
Delete |
In the Unfinished Products row, the system displays a purchase order commitment for WBS element T-10###.
To check this, select another element in the structure display other than the top WBS element. The system does not display any commitment values.
Evaluating costs in detail
The line item report displays each purchase order item separately.
The purchase requisition document appears.