Planning Revenues Using the Sales Order 
Usage
You plan the expected revenues using a billing plan for the sales order. This refers to the billing milestones in the project.
Prerequisites
You have called up the structure overview for your project in the project information system.
Evaluating Revenues in the Structure OverviewProcedure
This is the first sales document item in the structure below the top WBS element (T-10### with ID #### 000010).
The Selection Criteria dialog box appears.
The billing milestones for the projects are transferred as dates into the billing plan.
Your billing plan contains three dates:
The item overview for the sales order appears.
The structure overview for the project information system appears.
The project displays the planned revenues from the billing plan for the sales order.
Result
You have created a billing plan for the sales order by referring to existing billing milestones on the turbine project structure. The project displays the planned revenues.

In Customizing for the Project System, the planner profile specifies that the planned revenues from the sales order are updated on the project using cost element 800000.