Evaluating Revenues in the Structure Overview 

Use

In the structure overview for the project information system you evaluate the project data according to the structure.

Procedure

  1. Call up the transaction as follows:
  2. Menu Path

    From the Project System node, choose Information System ® Structures ® Structure Overview

    Transaction Code

    CN41

  3. If required, enter PS information profile YIDES_130000 , then choose .
  4. Enter the following data:
  5. Field

    Data

    Project

    T-10###

    Additional selection criteria

    Delete

  6. Choose .
  7. Select project definition T-10###, and choose .
  8. In the PrRevPl000 column, the system displays the planned revenues for the WBS element.

  9. To transfer additional functions to the standard toolbar, choose Choose functions.
  10. The system shows a list of possible functions (left hand column). You can select functions from the left-hand column, and transfer them to the right-hand column using Drag & Drop.

  11. Use Drag & Drop to select the following functions:
  1. Choose Copy.
  2. These additional symbols are transferred to the standard toolbar.

  3. Remain in the report.