Deleting the Billing Plan for the WBS Element 

Usage

Within sales pricing you have planned the revenues in a billing plan for WBS element T-10###. Because you have now received a sales order and you want to plan the billing data, you delete the billing plan for the WBS element.

Prerequisites

You have called up the structure overview for your project in the project information system.

Evaluating Revenues in the Structure Overview

Procedure

  1. Select the row for the Turbines T-10### WBS element in the structure.
  2. Use the right mouse button to choose Object ® Change.
  3. The Change WBS Element: Basic Data screen appears.

  4. Choose Details ® Billing plan.
  5. This takes you to the billing plan that you maintained in sales pricing.

  6. Choose Billing Plan.
  7. Choose Yes from the dialog box.
  8. Choose .
  9. The structure overview for the project information system appears.

  10. Choose .
  11. No planned revenues are displayed on the project.

  12. Remain in the report.

Result

You have deleted the billing plan and thus the planned revenues on the billing element.