Procedure
Without Reference:
The Create Material Cost Estimate Without Quantity Structure screen appears.
For more information, see
For more information, see
If you do not enter a lot size, the system uses the lot size from the material master. You can change the lot size later, if desired.
If you have entered a transfer control ID in the costing variant, this ID is automatically proposed by the system. The costing variant also specifies whether you can change or enter the transfer control ID.
For more information, see
If you set this indicator, the system inserts a costing item of item category V (with description, cost component and cost element) in the
For more information, see
Date Control.The
list screen for unit costing appears.You can use the
detail screen for this. Place the cursor on the desired costing item, and choose .For more information, see
Creating Costing Items.If the costing variant contains a costing sheet, overhead or process costs are calculated automatically when you save the costing items. For further information, see
The material cost estimate is saved temporarily. You return to the Create Material Cost Estimate Without Quantity Structure screen. In addition to the Costing data and Dates tab pages, further tab pages were created. The material costs calculated and
costing status are displayed in the Costs tab page.You can analyze the costs or go back to the list screen of the unit cost estimate. The following options are available:
For more information, see
With Reference:
Choose Cost est. to search for the material cost estimate concerned. The dialog box Selection of material cost estimates - w/o qty struct appears. Enter the selection criteria and choose . The system displays a list of the material cost estimates found. Select the required material cost estimate with a double click.
The
You can use the
detail screen for this. Place the cursor on the desired costing item, and choose .For more information, see
Creating Costing Items.The costing items are saved temporarily.
For more information, see Step 10 of the above procedure.
Result
Price Update
If you created a
standard cost estimate , you can transfer the marked results into the material master record as the future standard price and the released results as the current standard price. For more information, see Updating Standard Prices.If you created a inventory cost estimate, you can transfer the results into the material master record as the tax-based or commercial price. For more information, see
Tax-Based and Commercial Prices.If you created a standard cost estimate, inventory cost estimate, modified standard cost estimate, or a current cost estimate, you can transfer the results into the material master record as the planned prices. For more information, see
Updating the Other Planned Prices.Use as Reference
You can use a material cost estimate as a reference for another one. For more information, see
Creating a Cost Estimate with Reference.See also: