Completing the Testing ScheduleYou complete the testing schedule to confirm that all scheduling activities have been completed for the storage conditions. The system documents this status as a task in the stability study.
You have assigned an inspection plan to all storage conditions in the testing schedule.
From the
SAP Easy Access
menu, choose
.
The initial screen for changing a stability study appears.
On the initial screen, enter the key of the stability study you want to process and then choose
Enter
.
The screen for changing the stability study data appears.
In the action box on the right side of the screen, choose the follow-up function
Complete Testing Schedule
.
A dialog box appears prompting you to indicate whether you want to complete the testing schedule and then return to stability study after performing this step.
Choose
Yes
.
The testing schedule is automatically completed, the stability study is saved, and the system returns to stability study in the change mode.
You can now print out the storage list .