Assign Work Stations to Rooms
After defining the individual work stations, you must determine which rooms a work station is responsible for. This assignment is required because surgeries are planned at the area level and from the planned areas, and the system is designed to recognize which work stations the patient is to come in contact with.
Example
The OR coordinating unit is responsible for all operating rooms
Pre-op room 1 is responsible for rooms 1 to 10
Check-in area for OR area 3 services room 3.
The work stations are configured for the surgery area. For more information, see Configure Work Stations in OR.
Enter the assignment of time stamps to work stations on the SAP Easy Access
screen by choosing .
One work station can serve one or more rooms.
Example
E_ZOP1 ZOP1 07.05.1998 31.12.9999
Meaning: The check-in area E_ZOP1 serves the ZOP1 room during the specified period of validity.