Assigned Values for Projects

The assigned value for projects is calculated from:

  • Actual costs of WBS element carrying budget

  • Statistical actual costs of WBS element carrying budget

  • Actual costs of subordinate WBS elements if these do not carry budget

  • Statistical actual costs of subordinate WBS elements if these do not carry budget

  • Commitments of WBS element carrying budget

  • Commitments of subordinate WBS elements if these do not carry budget

  • Maximum of plan and actual costs + commitments from assigned networks or orders

    For more information, see the Implementation Guide (IMG) under Project System Õ Costs Õ Planned Costs Õ Define Order Value Updating for Orders for Projects .

  • Debit from settlement to WBS element

  • Credit from settlement to budget-controlled object (internal order, WBS element)

Caution Caution

Not used for calculation of the assigned value:

End of the caution.
  • Actual costs with a cost element defined in Customizing for availability control as an exempt cost element

    For more information, see the implementation guide (IMG) under Start of the navigation path Project System Next navigation step Costs Next navigation step Budget Next navigation step Specify Exempt Cost Elements End of the navigation path .

  • Actual costs that resulted from a business transaction that does not belong to the valid business transaction groups of availability control

    This can happen if you have not defined ++ as a business transaction group in Customizing for tolerance limits .

    For more information, see the Implementation Guide (IMG) under Start of the navigation path Project System Next navigation step Costs Next navigation step Budget Next navigation step Define Tolerance Limits End of the navigation path .

  • Credits from settlement to an object that is not budget-controlled (for example, cost center)

  • Revenues