Business Transaction GroupAll business transactions are assigned to a transaction group in availability control.
You can define an action that the system is to execute if a transaction were to use too many assigned funds.
For more information, see Availability Control Actions .
For the following transaction groups, you can define tolerance limits for different actions in each budget profile. To do so, in Customizing:
For internal orders, choose
For projects, choose Project SystemÕ
Costs
Õ
Budget
Õ
Define Tolerance Limits
.
All transaction groups
This general transaction group simplifies entry and is useful if you do not want to define separate tolerance limits for every transaction group.
If a tolerance limit is defined for
all transaction groups
, you can still define a limit for
one
transaction group. This limit takes precedence before the "general" tolerance limit. The tolerance level and action defined for
all transaction groups
are ignored if additional entries are available for a specified transaction group.
Purchase Requisition
Purchase order
Project Orders
During planning for a project order, changes to the residual order plan are checked. The system also uses this transaction group to check the assignment and dependency of an order/network that already has assigned values.
Note
Postings to project orders are checked in the relevant transaction group, for example a purchase order from a project order is checked in the
purchase order
transaction group.
Goods withdrawal
Financial Accounting document
For postings in Financial Accounting
Controlling Document
For postings in Cost Accounting.
Budgeting
During the project, it is possible that the budget may be reduced, even though assigned funds already exist in the project. You require this transaction group to enable availability control to take into any account retrospective budget changes.
If this causes the assigned funds to exceed the tolerance limit of availability control, the system refers you to the error log when you check or save the budget. The log contains warnings or error messages issued by the system when the tolerance level was exceeded.
Funds reservation
(manual commitment)
Fixed prices in project