Report ReleaseThe number and sequence of the individual release statuses depend on the control points through which the reports must pass. You can adjust the status network to meet your requirements.
Release Stages
The person responsible can accept or reject the report in every release status. Accepting a report transfers it to the next release status. If a report is rejected, it is then deleted (see Example: Status Network for Release ).
Note
Your internal organization should ensure that the reason for the report being rejected can be corrected.
Bypassing Release
In the generation variant header, you use the
Initial release status
field to specify:
Whether a report must be released
A report can bypass release status altogether if you have defined CO (
Completed
) or RE (
Released
) as the initial status.
Which release status is to initiate release
This means that you can start at any point in the release process.