Determination of Basic Load The free capacity of a capacity is the difference between the total available capacity of the capacity (including the allowed overload) and the existing capacity load, that is, the
basic load.
The system uses as the standard interpretation of the basic load, the detailed scheduling capacity requirements of operations that are dispatched and have a confirmed capacity, that is, of operations:
That you have dispatched using the planning table for capacity leveling
If you dispatch an operation using a planning table, it is given the status
dispatched.
For which you or the system have set the Capacity confirmed indicator indicator
During the online capacity availability check, the dialog box appears in the event of insufficient capacity, and you can manually set the
Capacity confirmed
indicator, or cancel it.
During the capacity availability check in the background, the system sets the
Capacity confirmed
indicator after the check or after finite scheduling automatically, if necessary.
If you
specify the initial basic load
using the report RCCYLOAD, you can incorporate orders and operations in the basic load. The system sets the
Capacity confirmed
indicator for the incorporated operations.
You specify in the selection profile for the overall profile which capacity requirements the system interprets as a basic load; you enter this in Customizing for the
Availability check.
If you do not enter a profile, the system uses:
The standard profile SAPSFCG013 for production orders and process orders
The standard profile SAPPM_G013 for maintenance orders and service orders
The logic of the capacity availability check is based on a basic load that consists of dispatched operations and operations with confirmed capacity - as defined in the standard profile. Any other definition could lead to incorrect results in the capacity availability check. You are therefore advised to use only the standard settings.
Initial basic load requirement
When you use the capacity availability check for the first time or when you only use the availability check or the planning table irregularly for orders relevant to production, the basic load is usually not current; that is, it does not contain all the capacity requirements that are relevant to the capacity availability check. In this case, you should specify the basic load before the capacity availability check using the report RCCYLOAD. For further information, see Specify initial basic load (Report RCCYLOAD) .
Displaying the orders and operations in the basic load
If you want to display the capacity requirements of the planned orders and work orders with dispatched operations or operations with confirmed capacity, you call up the capacity evaluation using the standard overall profile SAPSFC010.