Yard Task Item Hierarchy
When adding items to the yard task item hierarchy tree, you can execute the following actions:
-
You can add a single item including all subitems, for example, move a truck including all loaded containers through the yard.
-
You can add a sequence of items, that is, yard order top-level items, for example, move a whole train from one rail track to another rail track.
-
You can add a group of items, that is, yard order grouping items or TU groups, for example, move a whole consist of rail cars to another rail track.
From this view, you can delete subitems from a yard task item hierarchy to allow for a temporary movement of items without its subitems. For example, take a truck for cleaning without its loaded container. This means that the item is still a part of the yard order but not a part of the yard task.
Items of a yard task are not identical to items of the yard order. However, they are still linked. For the item of a yard task, you can see that the Yard Order Item Number field has the same Item No. as that of the yard order item.
The yard task item hierarchy can be created in the following ways:
-
Planned yard tasks with yard order reference – You can create a yard task from a yard order and assign the items from the yard order.
-
Unplanned yard tasks with yard order reference – You can create a yard task from the yard task creation screen and enter the yard order number
-
Unplanned yard tasks without yard order reference – You can create a yard task from the yard task creation screen without any reference yard order number
Cross Docking of Items Between Two Yard Orders
The same item can be a part of an inbound yard order and it can be a part of an outbound yard order. You have to first check-in the inbound yard order and activate the outbound yard order. Then you create the cross docking yard task. In the General section of the yard task screen, you enter the inbound yard order as the Yard Order Number and the outbound yard order as the Destination Yard Order Number under Cross Docking. When you activate this yard task, the TU Control Flag automatically is deselected from the inbound yard order and gets selected in the outbound yard order.
Simple Cross Docking between two orders
-
First yard order reference is YO1
-
Destination yard order reference is YO2
|
Item Hierarchy |
Yard Order Item Number |
Source Parent TU |
Transportation Unit |
Destination Yard Order Item Number |
Destination Parent TU |
|---|---|---|---|---|---|
|
TRCK |
10 |
MAN777 |
30 |
||
|
→CNTR |
20 |
MAN777 |
TALU221036 |
40 |
When you enter the Yard Order Item Number as 10, the system derives the hierarchy from the yard order hierarchy in YO1. A subitem 20 was inserted by the existing hierarchy in YO1 below item 10. When you enter the target items 30, 40, the system executes a number of checks:
-
The destination item hierarchy has to have the same structure as the source item structure.
-
There are two possibilities regarding the destination items:
-
The destination items have a TU number assigned, then the TU number has to be the same as those in the TU column.
-
The destination items have no TU number assigned, then the system checks the basic properties for compliance between the TU and the destination item definition.
-
Complex Cross Docking Between Two Orders
|
Item Hierarchy |
Yard Order Item Number |
Source Parent TU |
Transportation Unit |
Destination Yard Order Item Number |
Destination Parent TU |
|---|---|---|---|---|---|
|
TRAN (Group) |
10 |
10 |
|||
|
→RLCR |
20 |
31816650286 |
20 |
||
|
→→CNTR |
30 |
31816650286 |
TALU221036 |
30 |
|
|
→CONS (Group) |
40 |
Trainsection1 |
40 |
||
|
→→RLCR |
50 |
31816650287 |
31816650287 |
50 |
|
|
→→→CNTR |
60 |
31816650287 |
TALU221037 |
60 |
|
|
→→→CNTR |
70 |
31816650287 |
TALU221038 |
70 |
|
|
→→RLCR |
80 |
31816650288 |
80 |
||
|
→→→CNTR |
90 |
31816650288 |
TALU221039 |
90 |
The destination part of the yard task item hierarchy is non-editable when the activity type is non-movement. If grouping items are part of the yard order hierarchy definition, then they are also taken over into the yard task hierarchy. There can be several grouping items at different levels. The entire hierarchy, including grouping items, can be mapped to items of the destination yard order. In the above example, in the case of a train, the item numbers in source and destination order are identical.