Setting Up Engineered Labor Standards with BRFplus

This is one of the methods you can use to define engineered labor standards (ELS). You can use ELS in BRFplus to calculate the planned duration (normal time) of a planned workload and the adjusted planned duration (normal time) of an executed workload.

Prerequisites

  • You have activated Labor Management in Customizing for Extended Warehouse Management, under Start of the navigation pathLabor Management Next navigation step Activate Labor ManagementEnd of the navigation path.

  • You have activated the usage of BRFplus for ELS for your warehouse number in Customizing for Extended Warehouse Management, under Start of the navigation pathLabor Management Next navigation step Activate Labor ManagementEnd of the navigation path.

Use

You define rules in BRFplus for the ELS to calculate the normal time of workloads. You assign these rules to the corresponding decision service. When calculating the normal time, the ELS consider context-dependent information such as product, location, and reference document data.

You can use the result of the labor activity determination as input for the ELS. For more information, see Determination of Labor Activities for Planned and Executed Workloads.

You can use the reuslt of the travel distance calculation as input for the ELS. For more information, see Configuring the Travel Distance Calculation and Travel Time Using BRFplus.

Decision Services

EWM provides the following predefined, default decision services for calculating the planned duration (normal time) of planned workloads:

Decision Service

Application

Context

/SCWM/LM_ELS_CALC_HU

/SCWM/LM_ELS_SYS

ELS for Handling Unit

/SCWM/LM_ELS_CALC_HU_I

/SCWM/LM_ELS_SYS

ELS for Handling Unit Item

/SCWM/LM_ELS_CALC_VAS

/SCWM/LM_ELS_SYS

ELS for VAS Activity

/SCWM/LM_ELS_CALC_WHOPI

/SCWM/LM_ELS_SYS

ELS for Warehouse Order for Physical Inventory

/SCWM/LM_ELS_CALC_INV_I

/SCWM/LM_ELS_SYS

ELS for Physical Inventory Item

/SCWM/LM_ELS_CALC_WHOWT

/SCWM/LM_ELS_SYS

ELS for Warehouse Order for Warehouse Task

/SCWM/LM_ELS_CALC_WT

/SCWM/LM_ELS_SYS

ELS for Warehouse Task

EWM provides the following predefined, default decision services for calculating the adjusted planned duration (normal time) of executed workloads:

Decision Service

Application

Context

/SCWM/LM_ELS_CALC_EWL

/SCWM/LM_ELS_SYS

ELS for Executed Workload (No Context)

/SCWM/LM_ELS_CALC_IL

/SCWM/LM_ELS_SYS

ELS for Indirect Labor

/SCWM/LM_ELS_CALC_RH

/SCWM/LM_ELS_SYS

ELS for Receiving HU from Production

/SCWM/LM_ELS_CALC_RV

/SCWM/LM_ELS_SYS

ELS for Receiving HU from Vendor

/SCWM/LM_ELS_CALC_VAS

/SCWM/LM_ELS_SYS

ELS for VAS Activity

/SCWM/LM_ELS_CALC_WHOPI

/SCWM/LM_ELS_SYS

ELS for Warehouse Order for Physical Inventory

/SCWM/LM_ELS_CALC_INV_I

/SCWM/LM_ELS_SYS

ELS for Physical Inventory Item

/SCWM/LM_ELS_CALC_WHOWT

/SCWM/LM_ELS_SYS

ELS for Warehouse Order for Warehouse Task

/SCWM/LM_ELS_CALC_WT

/SCWM/LM_ELS_SYS

ELS for Warehouse Task

You can find a detailed description of each decision service, including the signature, in the system.

You can replace the default decision services for the time calculations with your own decision services. You need to assign these to the specific context in Customizing for Extended Warehouse Management, under Start of the navigation pathLabor Management Next navigation step Assign BRFplus Application and Function to Decision Service ContextEnd of the navigation path.

Business Add-Ins

You can make your own enhancements for each context, for example, if you want the time calculation in BRFplus to consider additional information. For this purpose, each decision service call is encapsulated by a Business Add-In (BAdI). Each BAdI provides a fallback implementation which calls either the standard decision service or the decision service you specify in Customizing. The following tables provide an overview of each BAdI and which method is used for which context, and which decision service is called in the fallback implementation.

For calculating the planned duration (normal time) of planned workloads:

BAdI Definition

Method

Standard Decision Service

/SCWM/EX_LM_ELS_HU

DETERMINE_PWL

/SCWM/LM_ELS_CALC_HU

/SCWM/EX_LM_ELS_HU_I

DETERMINE_PWL

/SCWM/LM_ELS_CALC_HU_I

/SCWM/EX_LM_ELS_VAS

DETERMINE_PWL

/SCWM/LM_ELS_CALC_VAS

/SCWM/EX_LM_ELS_WHOPI

DETERMINE_PWL

/SCWM/LM_ELS_CALC_WHOPI

/SCWM/EX_LM_ELS_INV_I

DETERMINE_PWL

/SCWM/LM_ELS_CALC_INV_I

/SCWM/EX_LM_ELS_WHOWT

DETERMINE_PWL

/SCWM/LM_ELS_CALC_WHOWT

/SCWM/EX_LM_ELS_WT

DETERMINE_PWL

/SCWM/LM_ELS_CALC_WT

For calculating the adjusted planned duration (normal time) of executed workloads:

BAdI Definition

Method

Standard Decision Service

/SCWM/EX_LM_ELS_EWL

DETERMINE_EWL

/SCWM/LM_ELS_CALC_EWL

/SCWM/EX_LM_ELS_IL

DETERMINE_EWL

/SCWM/LM_ELS_CALC_IL

/SCWM/EX_LM_ELS_RH

DETERMINE_EWL

/SCWM/LM_ELS_CALC_RH

/SCWM/EX_LM_ELS_RV

DETERMINE_EWL

/SCWM/LM_ELS_CALC_RV

/SCWM/EX_LM_ELS_VAS

DETERMINE_EWL

/SCWM/LM_ELS_CALC_VAS

/SCWM/EX_LM_ELS_WHOPI

DETERMINE_EWL

/SCWM/LM_ELS_CALC_WHOPI

/SCWM/EX_LM_ELS_INV_I

DETERMINE_EWL

/SCWM/LM_ELS_CALC_INV_I

/SCWM/EX_LM_ELS_WHOWT

DETERMINE_EWL

/SCWM/LM_ELS_CALC_WHOWT

/SCWM/EX_LM_ELS_WT

DETERMINE_EWL

/SCWM/LM_ELS_CALC_WT

For more information, see the Enhancement Spot for ELS Determination (/SCWM/ES_LM_ELS).

Example

You want to calculate the normal time for an executed workload of a warehouse order. This is a pick warehouse order containing three warehouse tasks, each with different products and different units of measure.

When the warehouse order is confirmed, one executed workload is created for which the labor activity is determined and the travel time is calculated. The results are provided as input for the normal time calculation. The decision service ELS for Warehouse Task is called separately for each warehouse task of the warehouse order. The results from each calculation per warehouse task are summarized and passed on as an input value to the decision service ELS for Warehouse Order for Warehouse Task. This decision service is called at the end to calculate the overall normal time of the executed workload for the warehouse order.

This example uses the following, simplified data for the warehouse order, labor activity, and travel time:

Warehouse Order

Labor Activity

Travel Time

1

OPIPA

4min 27s

This example uses the following, simplified data for the warehouse tasks:

Warehouse Task

Product

Quantity

Unit of Measure

1

PROD-S01

10

PC

2

PROD-S02

5

CAR

3

PROD-S03

1

PAL

Calculating the Normal Time for Each Warehouse Task

The decision service ELS for Warehouse Task is called for each of the warehouse tasks. The labor activity is provided as input and it determines how the normal time is calculated. For example, the labor activity code SCRAP might have a fixed time of 100 seconds per warehouse task, but here we have the labor activity code OPIPA. OPIPA does not have a fixed time. Instead, it requires a second step to calculate the normal time.

Labor Activity Code

Normal Time

SCRAP

100s

OPIPA

"Calculate time per unit of measure"

For OPIPA, the calculation of the normal time depends on the unit of measure and the corresponding quantity. The rules define different times for different units of measure, because the size and shape of an object influence the amount of time it takes to pick; for example, a worker requires more time to pick a carton from a shelf than a single piece.

The following table is a simplified representation of the normal time calculation per unit of measure:

Quantity

Unit of Measure

Normal Time per Warehouse Task

10

PC

(5s per piece) + (10s offset)

5

CAR

(10s per carton) + (20s offset)

1

PAL

(5min per pallet) + (40s offset)

Given the above data, the normal time per warehouse task is calculated as follows:

Warehouse Task 1: (10 PC * 5s) + 10s = 60s

Warehouse Task 2: (5 CAR * 10s) + 20s = 70s

Warehouse Task 3: (1 PAL * 5min) + 40s = 5min 40s

The normal times of all the warehouse tasks in this warehouse order are added together to give 7min 50s (= 60s + 70s + 5min 40s). The result is passed on to the decision service ELS for Warehouse Order for Warehouse Task.

Calculating the Normal Time for the Warehouse Order

The normal time per warehouse task contains the time required for each pick. We also need to add the times for the movements between the picking locations. For this we need the travel time, which is provided as input to the decision service. We also add a fixed offset of 4 minutes to the overall normal time to account for the time a worker requires to read the information about the warehouse tasks.

Using this information, the rules of the decision service ELS for Warehouse Order for Warehouse Task calculate the sum of the pick duration per warehouse task, the travel time between the individual pick locations, and the fixed offset for reading the information. The overall normal time for the warehouse order, thus the executed workload, is calculated as follows:

Normal Time: (Sum of Warehouse Tasks) + (Travel Time) + (Time for Reading Information)

Normal Time: (7min 50s) + (4min 27s) + (4min) = 16m 17s