Background documentationPlanning Functions

 

Planning functions support project planners in performing activities such as automatic valuation of cost and revenue calculations, revaluations, forecasting, simulations, and so on. Besides these planning functions, standard planning functions are also available for operations such as copying data, inserting new items, deleting items, distributing quantity with reference to cost or revenue, and so on. These planning functions are available in the planning sheet through the Analysis ribbon.

Project Cost and Revenue Planning provides planning functions for weekly and monthly planning. The weekly planning functions can be used for daily planning whereas the monthly planning functions support planning for quarterly and yearly horizons.

Features

  1. You calculate the cost and revenue of resources based on rates in the ERP system, resource types, and transaction and plan currency. (see Valuating Cost and Revenue)

  2. You distribute the cost or quantity across a particular periodic breakdown in the planning sheet. For more information, see Distributing Key Figures.

  3. You forecast the estimated cost for completing a project. For more information, see Estimate to Complete (ETC).

  4. You forecast the estimated cost at completion. For more information, see Estimate at Completion (EAC).

  5. You forecast the progress of a project by indicating the percentage of completion. For more information, see Percentage of Completion (POC).

  6. You recalculate cost and revenue figures when there are changes to the key figures in the planning sheet.