Project Cost Status
You use this report to track the cost performance of a project.
Integration | Data |
|---|---|
Scenario with | This scenario considers the plan data from |
Scenario without | This scenario considers the actual data from SAP ERP. |
This report allows you to:
Assess project performance
Identify areas that require attention
Prepare for status meetings
Notify status issues
Match plan and actual data in a flexible manner (see Data Enrichment)
Customize summarizations of data (see Customizing for SAP Commercial Project Management
under )
Note
The planned data in the Project Cost Status
report comes from Project Cost and Revenue Planning
. If Project Cost and Revenue Planning
is not integrated, or if the master project does not have an active plan version, the report only shows the actual data from SAP ERP.
To view the planned and actual data from SAP ERP, you can use the Project Cost & Revenue Analysis
report.