Data Enrichment
In SAP Commercial Project Management
, you plan costs and revenues against resources and resource types. For example, you can plan costs for the resource Consultant
and the resource type Labor
. Since
actual costs and revenues are posted against cost elements in SAP ERP, the system requires the actual data records to be enriched with the characteristics resource and resource type, for comparing the planned versus actual values.
With data enrichment, each actual record also carries data of the resource type and resource for the record. You use Business Rules Framework plus (BRFplus) rules to enrich the resource and resource type. For more information, see Rule-Based
Analytics. Once the resource type and the resource have been determined in BRFplus, you must define the key figure elements in Customizing for SAP Commercial Project Management
under . With this Customizing activity, you enrich the actual record with key figure elements. These key figure elements are used in the analytical reporting for data grouped according to business needs. With this Customizing activity,
you map the value of the actual record to the key figure (for example, the actual cost or the actual revenue), which is shown in the Project Cost Status
report.
Example
With this configuration, the Project Cost Status
report shows the following data:
Resource Type |
Resource |
Planned Cost (from SAP Commercial Project Management) |
Actual Cost (from Controlling (CO)) |
Labor |
Architect |
1500 |
1200 |
Labor |
Consultant |
1000 |
1100 |