Forecasting
You forecast cost during the execution phase based on the planned cost and the actual cost. Project Cost and Revenue Planning
provides three standard forecast queries:
Estimate to complete (ETC) (see Estimate to Complete (ETC))
The workbooks for ETC forecast allow forecasting based on cost and quantity.
Estimated at completion (EAC) (see Estimated at Completion (EAC))
Percentage of completion (POC) (see Percentage of Completion (POC))
Note that you can also define your own queries.
You have the required roles and authorizations.
Financial plans linked with master project structures (also known as execution structures) are available in the system.
SAP BusinessObjects Analysis, edition for Microsoft Office
is installed on your system. This is required to enable a Microsoft Excel-based spreadsheet for planning.
You have made the required settings in Customizing for SAP Commercial Project Management
under :
Define Plan Scenarios
Define Resource Types
Define Resources
Define Plan Types
You can execute forecasts for plan versions either by selecting a plan version or by selecting a structure element from the bid or master project structure.
You can forecast only at monthly intervals, starting with the first month of the plan period. Forecasting is supported only in plan types based on monthly or fiscal period intervals.
Special workbooks are available for different types of forecasting.
You can use the following rates to forecast ETC cost:
Planned rates – copy the planned rates to forecast periods. You can retrieve planned cost and revenue rates using the Get Plan Rates
button in the forecasting workbook.
Valuation rates – use the valuation strategy to determine rates for the forecast period
Manual input – enter your own rates for the forecast period
Note
The rates used in the planning sheets for forecasting are specific to these sheets and do not affect planned rates.
You can include new resources that have not been planned earlier, by using the Insert
button from the Financial Planning
group. This allows you to consider actual quantities for such resources and include them in ongoing forecasts.
You can run a background forecasting job for multiple projects using the /CPD/PFP_MASS_FORCAST_TRANSFER
program. With this program, you can forecast on projects without launching the workbook and transfer data to Controlling
(CO).
You can manually adjust the system-determined forecast values for a limited set of structure elements in the project structure. These structure elements can be added to a watch list, which is created in the Project Cost Status
report. You can edit the watch list in the financial plan header. From the financial plan header, you can launch the workbook for further forecast adjustments.
If you use Project Issue and Change Management
, when a change request is approved, the system automatically updates existing forecasts with the approved quantities and costs.
For output-based forecasting, you can activate the setting of PoC thresholds for forecasts. You do this for a selected master project type, in Customizing for (in the Financial Plan
section of the Define Master Project Types
view).
Forecast snapshots are a special version type, to store the forecast information of a previous period, when forecasts are created for successive periods of a financial plan.
The system creates a forecast snapshot only if this setting is enabled for the plan scenario (in the Customizing activity Define Plan Scenarios
). To create a forecast snapshot version, you must also ensure that snapshot versions can be created from version types linked to the plan scenario. To ensure that this is possible, you must create a version type for forecast snapshots and assign this to the version types in the plan scenario.
Note
If you do not assign a snapshot version type to version types in the plan scenario, the system does not create forecast snapshots during forecasts.
If you skip periods while forecasting, the system does not create forecast snapshots for skipped periods, but only for the periods for which forecasts were created.
Example
Suppose a plan period from January to December where you create forecasts for January, February, and April. The system creates a forecast snapshot for January when you forecast for February. When you forecast for April, the system creates a forecast snapshot for February. The next forecast snapshot version will be created for April, when you forecast for May or another period.
When you wish to forecast, you must also choose a month. The selected month becomes the forecast period for the forecast version. The forecast period of the forecast version changes each time you forecast for another period.
Note
If you create forecasts by skipping intermediate periods, you cannot return to create forecasts for skipped periods. Consequently, the system does not create forecast snapshot version for skipped periods.
In in-period forecasting, the user can forecast ETC values for the current period, based on actuals that occur during the period.
In forecasting workbooks (other than for quantity management), the rates are handled as follows:
The system uses plan rates from the first period as the proposed forecast rates for the entire duration of the financial plan. By default, this is the rate on which forecast costs and revenue are calculated for all successive forecast periods.
You can manually change proposed forecast rates in the input-ready fields of the workbook. However, this overwrites the proposed rates.
You can use the Valuate
button in the Financial Planning
group, to run valuation strategies and fetch valid rates from the system.
To fetch the originally proposed rates, use the Get Plan Rate
button in the Financial Planning
group.
Note
Using Valuate
or Get Plan Rates
button overwrites all manual entries.
In the forecast workbook, the Calculate EAC
function is only applicable to changed records (delta) of the selected structure element in the selection-option workbooks.
In the forecast workbook, when you make changes to the ETC values, the system automatically updates the EAC values.
In the forecast workbook, when you select a summary node, the planning function will only work only for the selected node, and not for its subnodes.