Determining the Costing Sequence

Prerequisites

Choose Start of the navigation path Accounting Next navigation step Controlling Next navigation step Product Cost Controlling Next navigation step Actual Costing/Material Ledger Next navigation step Actual Costing Next navigation step Edit Costing Run. End of the navigation path

You have performed a selection for the costing run and you have checked the results.

For more information, see Performing a Selection .

Procedure

  1. Under Process a nd Determine Sequence choose Parameters.

  2. Enter the necessary data and check the method of processing.

  3. You can have the system perform the function in the background when dealing with large amounts of data.

  4. Choose Execute .

Result

The system calculates the sequence that the costing run will follow.

You see a list of the manufacturing levels (for example, level 1 contains raw materials, level 2 contains semifinished goods, and so on) with a hierarchical list of the materials that were processed by the system. You can see more information in the log.

Next, perform single-level price determination for the costing run.

See also:

Allowing Material Price Determination

Performing Single-Level Material Price Determination .