Manage Material Coverage (F0251A)
-
Creation of MRP change requests for changes to existing purchase orders or stock transport orders
-
Additional options to accept and resolve coverage issues from the Actions column
-
New column for MRP element issues
-
Export into a spreadsheet
-
Navigation to source material
-
Default values for filtering
-
Material selection identifier
Technical Details
|
Type |
Changed |
|
Functional Localization |
Not applicable |
|
Scope Item |
J44 (Material Requirements Planning) |
|
Technical Object Name |
App ID: F0251A |
|
Preparation Required |
No |
|
Latest Reference Content Version Required |
No |
|
Application Component |
PP-FIO-MRP (Fiori UI for Material Requirements Planning) |
|
Valid as Of |
SAP S/4HANA Cloud 2308 |
Additional Details
Creation of MRP Change Requests
-
Change Purchase Order
If you choose this option, the order is changed directly without change request.
-
Change Requested
If you choose this option, the system automatically creates a change request with the status Requested for the specified changes.
- Request Change Later
If you choose this option, the system automatically creates a change request with the status New for the specified changes. You can send it to your supplier later from the Create MRP Change Requests app.
You can use the Create MRP Change Requests app to display or process your change requests afterwards. The request status is always reflected in the Status column of the Manage Material Coverage (F0251A) app. After a change request was applied, the system also updates the delivery date and quantity that is displayed in the stock / requirements list.
MRP Element Issues
- Receipt Element Past Due
- Reschedule In
- Reschedule Out
- Plan Process According to Schedule
- Cancel Process
- Excess Stock
- Excess Individual Segment
Depending on the issues that were detected, the system can propose rescheduling actions to help you prevent material shortages. You can perform these actions from the enhanced Actions column.
Actions for Material Coverage Issues
-
Reschedule In
-
Reschedule Out
-
Cancel Process
Export into Spreadsheet
You can now export the material overview and the stock / requirements list of a selected material into a spreadsheet file. The spreadsheets include all information that is provided in the corresponding table at the time of the export.
Navigation to Source Material
-
Dependent requirements (DepReq)
-
Dependent reservations (OrdRes)
Default Values for Filtering
You can now define user-specific default values for filtering using the settings that are available from the user actions menu. Default filter values are automatically applied to all apps that reference them and support the default values option.
Material Selection Identifier
-
material number
-
MRP area
-
plant
-
individual segment
By using this filter, you can specify multiple filter criteria in one step instead of entering filter values into individual filter fields. You can also use a combination of material selection identifier and individual filter fields to filter the material list.
If you navigate to this app from the Monitor Material Coverage - Net Segments or Monitor Material Coverage - Net and Individual Segments app, the material selection identifier is automatically selected based on the selection criteria that you specified in the relevant Monitor Material Coverage app. You can change this selection according to your requirements.