Generate Tasks and Processes Along the Driving Dimension
Use a wizard in the calendar to generate tasks and processes from an organizational
dimension.
Prerequisites
You need an existing process that is not in final status and not yet due.
Context
If you have a process and want to quickly add tasks and processes to it, use the
Tasks/Processes by Driving Dimension wizard. You will be
able to select a hierarchy from the dimensions and select specific members in the
hierarchy.
Procedure
-
In the calendar, select an Inactive or In
Progress process.
-
Choose .
The task generation wizard appears.
-
Select a model and the dimension to use as the driving dimension, and then
select Next.
-
Set the attributes for defining assignees or reviewers, and then select
Next.
-
Select the members of the hierarchy to include as processes or tasks.
The leaf members are generated as tasks and all other levels become
processes.
-
Select Next.
-
Set a prefix or use the default process name.
The combination of prefix and task or process name helps you find the related
tasks in the calendar.
-
Select Next.
-
Preview the list of tasks and processes.
If you want to make changes, you can select Back to go
back through the wizard and update your selections.
-
If everything looks correct, select Generate.
Your tasks and processes are generated and added to the calendar.
Results
When there are too many tasks to display in the Calendar view, a number
appears. Select that to see the total number of tasks. In the
Gantt view and in the List view
the hierarchy is collapsed and can be expanded.