Maintain Planning Profiles

In this step, you:

To be able to carry out project revenue planning, you must create a plan profile or use an existing one.

The following parameters are relevant to project cost planning:

Here, you define the following:
The indicator determines whether planning is by the bottom-up procedures:
If you set the indicator, the system automatically totals up the cost values each time you save and check them. The higher-level WBS element receives the total plan values for the WBS elements beneath it as its structure plan value.

Prerequisites

You must first have processed the following menu items and parameters, so that they are available as default values:

Revenue elements are cost elements defined with cost element type 11.

Action

1. Use "Detail" to check the plan profiles delivered as standard in the SAP System.
2. Change the details as necessary in the plan profiles, or create new ones as appropriate.

Additional information

You have the following alternative ways of assigning a plan profile to a project: