In this step you can specify how the
requirements should be distributed over the duration of an activity. The
requirements can be dispatched uniformly or individually to one or several
dates.
You determine distribution by means of a
distribution function and a
distribution strategy:
This function
determines how much of the capacity is consumed after a certain percentage of
activity duration.
This strategy
determines whether
- the capacity requirement is dispatched at the
earliest or latest start date.
- the requirement is distributed discretely to
the points defined in the function, or as a straight line, according to the
definition of the distribution function.
- the Gregorian calendar, the factory calendar
or the
operating time from the work center is used as a time
basis