Process for Capacity Requirements Planning in
Plant Maintenance 
In Plant Maintenance, you use capacity requirements planning if you want to maximize the capacity of the individual work centers for work scheduling, in view of the changing daily requirements.
If you want to use capacity requirements planning for Plant Maintenance effectively in your company, you need knowledge of the following areas:
· Work center in Plant Maintenance
Refer to The Work
Center (PM and CS) and
The Work Center
(PP/General).
· Planning elements in Plant Maintenance:
· Knowledge of Personnel Administration (application component PA-PA) and Time Management.
To optimize your use of capacity leveling, you must make certain settings in the Customizing for Plant Maintenance. The settings are usually made by your system administration.
For more information, see
Settings and Profiles
for Capacity Leveling.
...
1. Capacity requirements arise in Plant Maintenance from tasks that are requested in the form of orders. The capacity requirements requested and scheduled match the limited available capacity of the work centers and individual persons.
2. The maintenance planner enters the required work center in the order operation, schedules and saves the order. The system provisionally plans the requested capacity requirement to the work center. This means that initially the work is planned, but “not binding“ for this work center.
3. If the planning has been completed as far as possible, the planner can check the capacity availability, which they have entered for the operations. The capacity requirement for other orders or other operations is considered for this work center.
For more information, see
Capacity Availability
Check.
4. Owing to the number of orders resulting from both unplanned maintenance and preventive maintenance, it is often not possible to utilize all of the available work centers and persons equally when the order is created. Usually, some will have less capacity than is planned, whilst others will have more.
To utilize resources fully, the maintenance planner must regularly perform capacity leveling. To do this, the planner selects the graphical or tabular planning board, and then uses the functions available for capacity leveling.
For more information, see:
Display and Change of the Available Capacity