Function documentation Generate cProjects Roles Based on Strategic Demand Locate the document in its SAP Library structure

Use

With this function you can do the estimated capacity planning for the project according to the capacity views defined for it. Once the planning is finalized, you can transfer this planning data to the operational cProjects project role. The transferring of the planning data to the underlying cProjects project includes the following:

·        Creation of new roles in the underlying cProjects project for the capacity category/group at your discretion and transfer the planning data to the operational data in the role.

·        Transfer planning data in the portfolio item to the already existing role for the linked cProjects project.

Integration

You can enter required capacity for the role in the cProjects project.

Note

If the capacity planning data is transferred to this existing role, the required capacity is overwritten .

Prerequisites

·        There is an underlying cProjects project.

·        You have set the Download to cProjects indicator for at least one of the capacity views in Customizing of SAP xApp Resource and Portfolio Management (SAP xRPM) ® Global Customizing ® Portfolio-Independent Settings ® Define Financial and Capacity Views.

Features

For a portfolio item, the capacity data is maintained in the capacity planning area. Here the data is segregated into capacity category and capacity groups according to your requirement. The capacity data entered has also the classification based on the type of data called capacity views.

If you set the Download to cProjects indicator for certain capacity views in Customizing, the capacity data entered to these views can be downloaded to cProject roles.

Note

The data transfer from capacity planning to cProjects role is only supported for one occurrence. That is, once the system has transferred the data for a specific category, group, or view to a cProjects role, you cannot retransfer this data once again.

Activities

...

       1.      To download the capacity data, on the Item Overview view, choose the Transfer Demand actions link. This leads you to a mapping list where you can enter the mapping.

       2.      If you have to create a new role for the capacity data entered in the capacity planning, in the drop down list of the Related Action column, you can select Create. In the mapping table, the Role Name is defaulted to the capacity category description. You can edit the description and overwrite the default name.

       3.      If you wish to transfer the data to an existing role in the underlying cProjects project, in the drop down list of the Related Action column, you select Existing Role. You can select roles available from the drop down in the Role Name column. If you choose an existing role, the system fills out Role Type and Role Function by default.

       4.      Once the mapping is done, click Transfer and save.