Show TOC

 Internal Order (Detail): Plan/Actual

Technical name: 0OPA_C11_Q0002

If you want to modify this query, note the special features of the 0CCA_C11 CO-OM-OPA: Costs and Allocations InfoCube

Use

This query is a regular report for the order manager. It provides an overview of the costs incurred on an internal order during the reporting time frame and the current fiscal year. It enables you to make an actual and plan cost analysis, taking cost elements and the corresponding variances into account.

Note Note

This query is contained in the workbook Internal Order (Detail): Plan/Actual .

End of the note.

For background information on the concept of queries, see Queries in Controlling .

Filters

InfoObject

Description

0CO_AREA

Controlling area (variable 0P_COAR; single value entry, required)

0CURTYPE

Currency type (fixed value 10, company code currency)

0FISCVARNT

Fiscal year variant (SAP exit variable 0P_FVAEX)

0COORDER

Order (variable 0COOR)

Rows

InfoObject

Description

0COSTELEMNT

Cost element

Columns

InfoObject

Description

Planned costs for current year

Planned costs in current fiscal year

Actual costs for current year

Actual costs in current fiscal year

Variance (%) current year

Percentage variance between actual and planned costs in the current fiscal year (actual - plan) / plan

Planned costs total

Planned costs throughout the reporting time frame

Actual cost total

Actual costs throughout the reporting time frame

Variance (%) total

Percentage variance between actual and planned costs throughout reporting time frame (actual - plan) / plan