CO-OM: Costs and Allocations (Delta Extraction) Technical name: 0COOM_C02
This InfoCube contains all costs and quantities on cost centers, internal orders, WBS elements, networks, network activities, and network activity elements that were downloaded from the source systems using delta extraction . The InfoCube also contains the partner information for the allocation relationships.
Note
Before you make entries in this InfoCube, you need to load the master data for orders, WBS elements, networks and network activities. If you do not do so, the system cannot determine the responsible cost center or enter it in 0COSTCENTER.
You can also use this InfoCube to access your own fields. For more information, see Customer-Defined Fields .
For background information on the concept of InfoCubes, see InfoCubes in Controlling .
The following queries can access this InfoCube:
0COOM_C02_Q0004: Cost Center Orders: Plan/Actual - Situation
0COOM_C02_Q0002: Account Assignment Objects for the Cost Center: Plan/Actual - Situation
0COOM_C02_Q0003: Cost Center: Plan/Actual - Situation
0COOM_C02_Q0005: WBS Elements for the Cost Center: Plan/Actual - Situation
0COOM_C02_Q0303: PSM: Cost Center: Plan/Actual - Situation
0COOM_C02_Q0304: PSM: Cost Center Orders: Plan/Actual - Situation
0COOM_C02_Q0305: PSM: WBS Elements for Cost Center: Plan/Actual - Situation
If you attempt to sum across different valuation views and currency types, your query results will be incorrect. Summing across different values of these characteristics does not provide useful information.
0CO_OM_CCA_9 Cost Centers: Actual Costs with Delta Extraction
0CO_OM_CCA_1 Cost Centers: Costs
0CO_OM_OPA_6 Internal Orders: Actual Costs Using Delta Extraction
0CO_OM_OPA_1 Internal Orders: Costs
0CO_OM_WBS_6 WBS Elements: Actual Costs Using Delta Extraction
0CO_OM_WBS_1 WBS Elements: Costs
0CO_OM_NTW_2 Network: Actual Costs Using Delta Extraction
0CO_OM_NTW_1 Networks: Costs
0CO_OM_NWA_2 Network Activity: Actual Costs Using Delta Extraction
0CO_OM_NWA_1 Network Activities: Costs
0CO_OM_NAE_2 Network Activity Elements: Actual Costs Using Delta Extraction
0CO_OM_NAE_1 Network Activity Elements: Costs
The InfoCube is supplied with information from the above mentioned InfoSources. This requires a special procedure when loading the data from the source systems into the Cube. We recommend the following procedure:
Create an InfoPackage for InfoSources 0CO_OM_CCA_9, 0CO_OM_OPA_6, 0CO_OM_WBS_6, 0CO_OM_NTW_2,0CO_OM_NWA_2 and 0CO_OM_NAE_2 to load the actual data.
Case A (with delta process): If you use the delta process, you can load your actual data at any time. You do not need to enter the period.
Case B (without delta process): If you do not use the delta process, it is best to load your actual data at the end of the period (after completion of the period-end closing process) by restricting the selection to the expired period.
Recommendation
SAP recommends the delta process.
To load the remaining data (such as plan, target or period-end closing) for InfoSources 0CO_OM_CCA_1, 0CO_OM_OPA_1, 0CO_OM_WBS_1, 0CO_OM_NTW_1, 0CO_OM_NWA_1 and 0CO_OM_NAE_1, create a separate InfoPackage for
each
type of data. This is necessary because of the different data transfer time points. Restrict selection to the relevant value type (such as
plan
) and the period or periods (such as
1 – 3
for the first quarter or
1 – 12
for the full year).
For more information on loading data, see InfoCubes in Controlling .
InfoObject |
Description |
0COSTCENTER |
|
0COORDER |
|
0WBS_ELEMT |
|
0NETWORK |
|
0PROJECT |
|
0ACTY_ELEMT |
|
0ACTIVITY |
|
0PROFIT_CTR |
|
0COSTELEMT |
|
0CO_AREA |
|
0CURTYPE |
|
0PIOJSV |
|
0IOBJSV |
|
0PIOVALUE |
|
0VERSION |
|
0VTDETAIL |
|
0VTYPE |
|
0VTSTAT |
|
0DB_CR_IND |
|
0VALUATION |
|
0METYPE |
|
0CHRTS_ACCTS |
|
0GL_ACCOUNT |
|
0CREDITOR |
|
0DEBITOR |
|
0AUXACCTYPE |
|
0AUXACCVAL |
|
0COMP_CODE |
|
0BUS_AREA |
|
0FUNC_AREA |
|
0PCOMP_CODE |
|
0PFUNC_AREA |
|
0PLANT |
|
0MATERIAL |
|
0EMPLOYEE |
|
0FM_AREA |
|
0FUND |
|
0FUNC_AREA |
|
0GRANT_NBR |
|
0PFUND |
|
0PFUNC_AREA |
|
0PGRANT_NBR |
Note
The system enters the responsible cost center for the order, WBS element, network, network activities, and network activity elements in the 0COSTCENTER (cost center) InfoCube. This takes place in the data records for orders, WBS elements, networks, and network activities.
The system determines the responsible cost center in the routine for the update rule from the master data of the order, WBS element, network, network activity, or the network activity element.
In data records for cost centers, entries are not made in the following InfoObjects: 0COORDER (order), 0WBS_ELEMT (WBS element), 0NETWORK (network), 0ACTIVITY (network activity) and 0ACTY_ELEMT (network activity element).
The following navigation attributes have been activated. This is a sample selection. You are free to activate additional attributes, or deactivate attributes to improve performance.
InfoObject |
Description |
0COORDER__0COORD_TYPE |
Order type |
0COSTCENTER__0PROFIT_CTR |
Profit center |
InfoObject |
Description |
0FISCPER |
|
0FISVARNT |
|
0FISCPER3 |
|
0FISCYEAR |
Note
The
fiscal year
(
0FISCYEAR
) and
posting period
(
0FISCPER3
) characteristics are filled by the
Fiscal year/Period
field (
0FISCPER
) in the InfoSource.
InfoObject |
Description |
0QUANTITYFX |
|
0QUANTITY |
|
0QUANTITYVR |
|
0AMOUNTFX |
|
0AMOUNT |
|
0AMOUNTVR |
The restricted key figures are divided into several groups.
Note
The basic key figures cannot be used without restricting some of the characteristics. For this reason you should use only the supplied restricted key figures in queries you have defined yourself, or analyze the supplied restricted key figures and modify them to suit your requirements.
InfoObject |
Restriction |
“Costs” Group |
|
Data for all restricted key figures of the group |
Sender/receiver = S (debit posting or receiver debit) Key figure category = 1000 (revenues and associated quantities) Valuation view = 0 (legal valuation) Version = 0 (current variant) Key figure = 0AMOUNT (amount) |
0COOM_C02_RK001 Actual costs |
Value type = 10 (actual) |
0COOM_C02_RK003 Planned costs |
Value type = 20 (plan) |
“Revenues” Group |
|
Data for all restricted key figures of the group |
Sender/receiver = H (credit posting or sender debit) Key figure category = 1001 (costs and associated quantities) Valuation view = 0 (legal valuation) Version = 0 (current variant) Key figure = 0AMOUNT (amount) |
0COOM_C02_RK005 Actual revenues |
Value type = 10 (actual) |
0COOM_C02_RK006 Planned revenue |
Value type = 20 (plan) |
“Credits” Group |
|
Data for all restricted key figures of the group |
Sender/receiver = H (credit posting or sender debit) Key figure category = 1000 (costs and associated quantities) Valuation view = 0 (legal valuation) Version = 0 (current variant) Key figure = 0AMOUNT (amount) |
0COOM_C02_RK008 Actual credit |
Value type = 10 (actual) |
0COOM_C02_RK009 Plan credit |
Value type = 20 (plan) |
InfoObject |
Description |
0CURRENCY |
|
0UNIT |