Process (Range): Costs - Plan/Actual - SituationTechnical name: 0ABC_C06_Q0001
Based on InfoCube: CO-OM-ABC: Costs and Allocations
This query is a regular report for the process manager. It provides an overview of the planned and actual costs of the current year for all selected objects. Reporting time frames are the previous period, the periods in the current year up to the current date (values are cumulated), and all periods of the current year (actual cost projection).
You must enter the controlling area when you call up the query. You can limit the displayed data further using the following:
The process
The cost element
Or both of the above
If you want to limit the processes, first select a hierarchy. You can then further limit the data by specifying a range of processes or a single process.
If you want to limit the cost elements, first select a hierarchy. You can then further limit the data by specifying a cost element group or a single cost element.
Note
This query is contained in the workbook Process (Range): Costs – Plan/Actual – Situation .
For background information on the concept of queries, see Queries in Controlling .
InfoObject |
Description of the Info Object (and restriction or calculation formula) |
0FISCVARNT |
Fiscal year variant (SAP exit variable &OP_FVAEX&: the system derives the fiscal year variant from the controlling area) |
0CO_AREA |
Controlling area (variable &OP_COAR&, controlling area, single value entry, mandatory) |
0CURTYPE |
Currency type = 10 (company code currency) |
InfoObject |
Description |
0COSTELMNT |
Cost element (variable &0N_COEL& (&0H_COEL&), cost element group (cost element hierarchy) |
Row Name |
Description (or Restrictions or Calculation Formula) |
0ABCPROCESS |
Business process number , variable &0N_ABC& (0H_ABC), business process area (business process hierarchy) |
Column Name |
Description (or Restrictions or Calculation Formula) |
If an SAP exit variable is used, the time periods for which the quantities are calculated are determined automatically (see also
Queries in Controlling
under
|
|
Actual costs &0T_FPER& |
Restricted key figure: Actual costs Characteristic: Fiscal Year/Period (Exit variable &0P_PRFP1&, SAP exit variable, previous period of the current fiscal year) |
Planned costs &0T_FPER& |
Restricted key figure: Plan costs Characteristic: Fiscal Year/Period (Exit variable &0P_PRFP1&, SAP exit variable, previous period of the current fiscal year) |
Actual Costs &0T_FPERY& YTD |
Restricted key figure: Actual costs Characteristic: Fiscal Year/Period (Variable &0FYTCFP&, SAP exit variable, cumulated up to current fiscal year period) |
Planned costs &0T_FPERY& YTD |
Restricted key figure: Plan costs Characteristic: Fiscal Year/Period (Variable &0FYTCFP&, SAP exit variable, cumulated up to current fiscal year period) |
Planned costs &0T_FPERY& |
Restricted key figure: Plan costs Characteristic: Fiscal Year/Period (variable &0I_CUFYE&, SAP exit variable, all periods of the current fiscal year) |
Variance |
Actual costs &0T_FPER& % planned costs &0T_FPER& |
Variance YTD |
Actual costs &0T_FPERY& YTD % planned costs &0T_FPERY& YTD |
Actual projection |
Actual costs &0T_FPERY& YTD x 12 / current period of the fiscal year (formula variable) |
Variance (projection) |
Actual projection % planned costs &0T_FPERY& |