PSM: Cost Center/Activity Type: Analysis - Target/Actual/Variance Technical name: 0CCA_C02_Q0304
If you want to modify this query, note the special features of the InfoCube 0CCA_C02 CO-OM-CCA: Costs and Allocations (by Activity Type) .
This query is an analysis report for the cost center manager. This query provides an overview of the incurred costs and consumption quantities on a cost center/activity type during the reporting timeframe.
For background information on the concept of queries, see Queries in Controlling .
InfoObject |
Description of InfoObject (or Restrictions or Calculation Formula) |
|---|---|
0CO_AREA |
Controlling area (variable 0P_COAR; single value entry, required) |
0CURTYPE |
Currency type (fixed value 10, company code currency) |
0FISCVARNT |
|
0METYPE |
Key figure category (fixed value 1010, split costs) |
InfoObject |
Description of InfoObject |
|---|---|
0FISCPER |
Fiscal year/period (variable 0I_FPER) |
0COSTELEMENT |
|
0FM_AREA |
|
0FUND |
|
0FUNC_AREA |
|
0GRANT_NBR |
0COSTCENTER |
Cost center (variable 0S_CCTR) |
0ACTTYPE |
InfoObject |
Description of InfoObject (or Restrictions or Calculation Formula) |
|---|---|
Target - split |
Split target costs distributed to the activity type during the reporting time frame (controlling area currency) |
Actual - split |
Split target costs distributed to the activity type during the reporting time frame (controlling area currency) |
Variance (%) |
Percentage variance between split actual and target costs |
Activity quantity -plan |
Plan quantities in the reporting timeframe |
Activity quantity - actual |
Actual quantities in the reporting timeframe |
Variance (%) |
Percentage variance between plan and actual quantities in the reporting timeframe |