Start of Content Area

Key figure APO Capacity Split Quantity (Multi-Activity Resource)  Locate the document in its SAP Library structure

Technical name: 0APO_INDRES

Use

To ensure a detailed shift and schedule planning in capacity planning, capacities can be divided into individual capacities (for example individual machines) and maintained for the available capacities. Capacity requirements can be assigned to, or scheduled for these individual capacities in the graphic or table planning board.

Technical data

Available as of release

SAP APO 3.0A

Unit

APO unit for a resource’s capacity (0APO_RUNIT)

Aggregation

Summation

Exception aggregation

Summation

 

 

End of Content Area