Actual Performance Efficiency Rate 3
Technical Name: 0C_A_PER3
Use
Planned/Actual Comparison: Operation/Work Center View:
This InfoObject calculates the actual performance efficiency rate of the 3. activity type.The actual performance efficiency rate is calculated from the target quantity of the 3. activity type, which was not corrected by the performance efficiency rate, divided by the actual quantity of the 3. activity type. This displays the efficiency of the work center.
Example
Confirmation of 8 tons, required time per ton 1 hour, configured performance efficiency rate 80%.
Adjusted target quantity without performance efficiency rate: 8 hours, with performance efficiency rate: 10 hours
{0>
Confirmed total quantity 12 hours, makes 8/12 = 67%<}100{>Confirmed total quantity: 12 hours, results in 8/12 = 67%<0}
Technical Data
|
Available from Release |
R/3 Release 4.0B |
|
Calculation |
'Tgt Qty/Actytype3 w/out PER' %A 'Actual Acty.3' |