Technical Name: 0C_A_EXECTMX_PP01
Use
Planned/Actual Comparison: Order/Material View:
This InfoObject calculates the average, exact actual execution time per production order.The exact actual execution time is calculated in a changeable unit and is made up from the difference in time between the actual execution start and the actual execution finish of the individual work centers. During the calculation, break times are calculated based on the shift schedule.
Technical Data
|
Available from Release |
R/3 Release 4.0B |
|
Calculation |
'Act-Exec time ex.' / 'Num.ProdOrd.' |