Start of Content Area

Target/Actual Deviation Finish +  Locate the document in its SAP Library structure

Technical name: 0C_OUTPUTDEVP

Use

Plan/actual comparison operation/work center view: This InfoObject calculates the average positive target/actual deviation for the operation finish.

A negative time specifies a delay in the schedule.

Technical Data

Available from Release

R/3 Release 3.0F

Calculation

"target/actual finish+" / "no. of manufacturing orders"

 

 

 