Key figure Build Cycle Time (SCOR)  Locate the document in its SAP Library structure

Technical name: -/-

(None, because calculated key figure is based on restricted key figures in the Yield_SCOR query).

Use

This SCOR Key Figure is used by the Build Cycle Time query (repetitive manufacturing, 0PP_C07_Q002_SCOR). This key figure determines approximately how long it takes to manufacture a production unit (either several units or the standard lot size). The build cycle time is the average production time for make-to-stock products. It is calculated by dividing the average number of units in production at any given time by the average daily production rate in units.

This key figure is the takt for production lines in repetitive manufacturing.

Prerequisites for use:

 

Example: Considerations about production line capacity

 

NoteNote

Technical Data

Available from Release

R/3 Release 3.0A

Calculation

Base Quantity/ (Confirmed Quantity/ Time Unit)

 

 

 

End of Content Area