APO Resource-dependent Time Buffer
Technical name: 0APO_BUFFTI
Use
This is a safety time that safeguards an activity (or independent resource on which the activity is being processed), against unforeseen delays in material staging.
The system uses this buffer during planning to schedule a larger time interval between the activity and the activities preceding it. This means that any delays in the preceding activities can be covered by the buffer in order to avoid any stoppage at the resource due to missing material. In this instance, preceding activities are activities that have a time-based or
Pegging relationship with the activity.Technical data
|
Available as of release |
SAP APO 3.0A |
|
Unit |
APO resource time buffer unit (0APO_BUFTIU) |
|
Aggregation |
Summation |
|
Exception aggregation |
Summation |