Start of Content Area

Key figure APO Resource-dependent Time Buffer  Locate the document in its SAP Library structure

Technical name: 0APO_BUFFTI

Use

This is a safety time that safeguards an activity (or independent resource on which the activity is being processed), against unforeseen delays in material staging.

The system uses this buffer during planning to schedule a larger time interval between the activity and the activities preceding it. This means that any delays in the preceding activities can be covered by the buffer in order to avoid any stoppage at the resource due to missing material. In this instance, preceding activities are activities that have a time-based or Pegging relationship with the activity.

Technical data

Available as of release

SAP APO 3.0A

Unit

APO resource time buffer unit (0APO_BUFTIU)

Aggregation

Summation

Exception aggregation

Summation

 

 

End of Content Area