Entire Target/Actual Activity Deviation in Percent
Technical Name: 0C_TA_ACT_%
Use
Planned/Actual Comparison: Operation/Work Center View:
This InfoObject calculates the percentage deviation of the actual activity from the adjusted target activity of the first three activity types.This key figure is only useful if the first three activity types in the unit are translated.
Technical Data
|
Available from Release |
R/3 Release 4.0B |
|
Calculation |
'-((‘Act.-Acty. 1' + ‘Act.-Acty. 2' + ‘Act.-Acty. 3') % (‘Tgt-Acty. 1 adjusted.' + 'Tgt-Acty. 2 adjusted.' + 'Tgt-Acty. 3 adjusted.') |