Dummy text Material View from PP/PP-PI  Locate the document in its SAP Library structure

Technical Name: 2LIS_04_P_MATNR

Technical Data

Type of DataSource

Transaction Data (Movement Data)

Application Component

Production Planning and Control (PP)

Available from OLTP Release

SAP R/3 4.0B

Available from Plug-In Release

PI 2000.1

RemoteCube Compatibility

Yes

Prerequisites

Activation of the DataSource.

Use

This structure is used to extract information in the production order header consistently to a BW system.

This provides the transaction data from the production process, with reference to the order header and item, and returns information about the production order header.

As of SAP R/3 4.0B, this DataSource replaces DataSource 2LIS_04_S280.

Delta Update

A Delta update is supported. Delta process: ABR – Complete delta with deletion indicators using delta queue (Cube-compatible).

Fields of Origin in the Extract Structure

Field in Extract Structure

Description of Field in the Extract Structure

Table of Origin

Field in Table of Origin

AUFNR

Order Number

 

 

BUKRS

Company Code

 

 

ERFDAT

Creation Date

 

 

FA_GLFT

Order Has Status GLFT

 

 

FTRMI

Actual Release Date

 

 

FTRMP

Planned Release Date

 

 

FTRMS

Scheduled Release Date

 

 

GETRI

Returned Order Completion

 

 

GLTRP

Basic Finish Date

 

 

GLTRS

Scheduled Finish

 

 

GSTRI

Actual Start Date

 

 

GSTRP

Basic Start Date

 

 

GSTRS

Scheduled Start

 

 

LEAD_LAUFNR

Leading Order in Current Processing

 

 

MAUFNR

Number of Superordinate Order

 

 

WERKS

Plant

 

 

BUDAT

Posting Date Actual Delivery/Finish Date

 

 

DFZEH

Unit Execution Time

 

 

DFZEXEH

Unit Execution Time (Exact)

 

 

ETRMP

Planned Order Creation Date

 

 

IAMNG

Actual Scrap Quantity Order Item

 

 

I_DFZ

Actual Execution Time

 

 

I_DFZ_EX

Actual Execution Time (Exact)

 

 

I_DLZ

Actual Lead Time

 

 

I_DLZ_EX

Actual Lead Time (Exact)

 

 

KDAUF

Sales Order Number

 

 

KEINH

Unit of Measure for Output of Available Capacity and Capacity Requirement

 

 

KSUMS

Target Capacity Requirement Sum

 

 

LTRMI

Actual Delivery/Finish Date

 

 

LTRMP

Delivery Date from Planned Order

 

 

MATNR

Material Number

 

 

MEINS

Base Unit of Measure

 

 

PAMNG

Fixed Quantity of Scrap

 

 

PGMNG

Total Planned Order Quantity

 

 

PI_FREI

Release Delivery Date Variation Plan/Actual

 

 

PI_LIEF

Delivery Date Variation Plan/Actual

 

 

PI_STAR

Start Schedule Variation Plan/Actual

 

 

PLNUM

Planned Order Number

 

 

POSNR

Number of the Order Item

 

 

PSAMG

Scrap Item Quantity

 

 

PSMNG

Item Quantity Order

 

 

PS_FREI

Release Delivery Date Variation Plan/Target

 

 

PS_LIEF

Delivery Date Variation Plan/Target

 

 

PS_STAR

Start Date Variation Plan/Target

 

 

PWERK

Planning Plant for the Order

 

 

P_DLZ

Plan Lead Time

 

 

SI_FREI

Release Date Variation Target/Actual

 

 

SI_LIEF

Scheduled Delivery Date Target/Actual

 

 

SI_STAR

Start Date Variation Target/Actual

 

 

STRMP

Planned Order Start Date

 

 

S_DFZ

Target Execution Time

 

 

S_DFZ_EX

Target Execution Time (Exact)

 

 

S_DLZ

Target Lead Time

 

 

S_DLZ_EX

Target Lead Time (Exact)

 

 

WEMNG

Goods Receipt Quantity

 

 

ZEITP

Result to which an Update Should Lead

 

 

LEAD_MATNR

Material Number of Leading Order

 

 

ROCANCEL

Cancellation of Data Record

 

 

 

 

End of Content Area