Start of Content Area

QueryCapacity Load Utilization  Locate the document in its SAP Library structure

0C_T_WAIT_TIME_PP04

Technical Name: 0PP_C04_Q001

Use

This query displays the capacity load utilization of a work center. However, you should note that a capacity requirement generated by an operation is not distributed across several days. Therefore, the query should be called up for longer periods of time, as the edge of the selection period can contain inaccuracies.

The available capacity is available per work center. This should be noted when drilling down on orders and operations.

The SCOR key figure Machine Wait Time shows you the proportion of a work center’s unused capacity in relation to the total capacity.

Contrary to query 0PP_C03_Q007 the first confirmation date of an operation is used as the date of the capacity requirement of an operation instead of the actual release date.

Note

If you have an R/3 Release from 4.0B onwards, SAP recommends that you use query 0PP_C13_Q001 for capacity evaluations.

Free Characteristics

InfoObject

Description

0WORKCENTER__0WRKCT_RESP

Person responsible

0WORKCENTER

Work center, variable &0S_WORKC2&

0MATERIAL

Material, variable &0S_MAT&

0PRODORDER

Order

0OPERATION

Operation

0S_OPERAT

Suboperation

0CALMONTH

CalYear/Month, variable &0I_CALMO&

0CALDAY

Calendar day

Rows

InfoObject

Description of InfoObject (or Restriction or Calculation Formula)

0PLANT

Plant, variable &0S_PLANT&

Columns

InfoObject

Description of InfoObject (or Restriction or Calculation Formula)

0C_T_CAPAUTIL_%_PP

Capacity load utilization

0C_T_CAPACITY_PP04

Target capacity requirements

0STANDCAP

Available capacity

0C_T_WAIT_TIME_PP04

Machine wait time

 

 

 

 

End of Content Area