Total Schedule Deviation: Order View
Technical Name: 0PP_C01_Q003
Use
This query compares the schedule deviations of order release, start and delivery. It therefore provides information on how well production is being planned.
Free Characteristics
InfoObject |
Description |
0PRODORDER__0MRP_CONTRL |
MRP controller, variable &0S_PDISP& |
0MATERIAL |
Material, variable &0S_MAT& |
0PRODORDER |
Order |
0CALMONTH |
CalYear/Month, variable &0I_CALMO& |
0CALDAY |
Calendar day |
Rows
InfoObject |
Description of InfoObject (or Restriction or Calculation Formula) |
0PLANT |
Plant, variable &0S_PLANT& |
Columns
InfoObject |
Description of InfoObject (or Restriction or Calculation Formula) |
| 0C_PTA_RELDEV |
Total deviation release |
| 0C_PTA_STARTDEV |
Total deviation start |
| 0C_PTA_DELDEV |
Total deviation delivery date |