Actual Performance Efficiency Rate 2  Locate the document in its SAP Library structure

{0>Technischer Name: 0C_A_PER2<}92{>Technical Name: 0C_A_PER2<0}

Use

Planned/Actual Comparison: Operation/Work Center View: This InfoObject calculates the actual performance efficiency rate of the 2. activity type.

The actual performance efficiency rate is calculated from the target quantity of the 2. activity type, which was not corrected by the performance efficiency rate, divided by the actual quantity of the 2. activity type. This displays the efficiency of the work center.

Example

Confirmation of 8 tons, required time per ton: 1 hour, configured performance efficiency rate 80%.

Adjusted target quantity without performance efficiency rate: 8 hours, with performance efficiency rate: 10 hours

Confirmed total quantity: 12 hours, results in 8/12 = 67%

 

Technical Data

Available from Release

R/3 Release 4.0B

Calculation

'Tgt Qty/Actytype2 w/out PER' %A 'Actual Acty.2'

 

 

 

 