You use this query to monitor the availability of work centers of a particular plant based on the selection criteria like plant, work center, and the date range.
Analysis on the basis of the following factors is carried out in the dashboard:
Availability per plant
Availability per work center
Availability per month for plant
Availability per month for work center
Availability per day of month
The results are aggregated at plant level and displayed in tabular views containing all work centers for the selected plant. By default, you can view all the work centers for a selected plant in the Month view. You can also view the results in the Work Center view.
The availability is calculated based on the formula Availability = Production Time / Total Time. The availability represents the percentage of the scheduled time that the work center is available to operate. This query is based on the InfoCube 0PP_MP16 and was developed for the business package for Production Supervisor.
Object Type | Name | Technical Name | Value Restriction / Calculation |
|---|---|---|---|
| Work Center |
0WORKCENTER |
|
| Material |
0MATERIAL |
|
| Calendar Year/Month |
0CALMONTH |
|
| Calendar Day |
0CALDAY |
Object Type | Name | Technical Name | Value Restriction / Calculation |
|---|---|---|---|
| Plant |
0Plant |
— |
Object Type | Name | Technical Name | Value Restriction / Calculation |
|---|---|---|---|
| Production Time |
0PP_MP_CK0022 |
— |
| Operating Time |
0USINGTIME |
|
| Availability% |
0PP_MP16_CK0007 |