Role documentation Shift Manager  Locate the document in its SAP Library structure

Technical name: SAP_BW_0ROLE_0081

Task Area

The shift manager, together with his team, is responsible for ensuring that the plan created by the production planner is carried out during a shift. His area of responsibility extends across a production area or one or more production lines.

The shift manager has personnel responsibility and sometimes also cost center responsibility for his area.

A shift manager has the following tasks:

Structure

Tasks in the Business Information Warehouse

The plant manager has administrative management functions and carries out operation/work center analyses as well as capacity and quality analyses. To accomplish these tasks, BW provides business content information in the form of workbooks. Each task corresponds to a cluster of one or more workbooks. The workbooks contain one or more queries that yield the relevant information. The tasks (clusters) are logically grouped together into task areas (subchannels). The following workbooks are available for shift managers:

Administrative Management Functions

Area to Analyze (Cluster)

Workbook

Cost center

Cost center report: plan/actual comparison

Controlling environment of cost center

Cost center responsible for orders, projects, and networks

 

Project report (WBS elements)

 

Order report

Human resources

Cost center: headcount FTE

Operation/Work Center Analyses

Area to Analyze (Cluster)

Workbook

Performance analysis

Performance efficiency rate target/actual

Production scheduling analyses

Lead time deviations (resource)

 

Schedule deviation (resource)

Production quantity analyses

Operation quantities

 

Target/actual material consumption

 

Plan realization

Quantities

Operation quantities

 

Target/actual material consumption

Actual data for exact periods

Actual activities

 

Actual quantities at the work center

 

Material consumption

Combination quantities/times

Execution time/scrap deviations (resource)

 

Quantities/scrap/lead time deviations (order)

 

Schedule and quantity deviations, work center view

Capacity analysis

Capacity load utilization, distributed requirement ((>= 4.0B)

 

Capacity load utilization, basis confirmation date

Duration schedule deviation

Lead time and relative schedule deviation: work center

 

Schedule deviations, work center view

Capacity Analyses

Area to Analyze (Cluster)

Workbook

Capacity analysis

Capacity load utilization, basis confirmation date

Downtime

Downtime according to categories

 

Target/net production times

 

Downtimes according to downtime elements

Quality Analyses

Area to Analyze (Cluster)

Workbook

Notifications

Notification analysis - quality management

 

Error analysis - notifications

Inspection results

Inspection results, rejection proportion

 

Inspection results, within tolerance range

Inspection lots

Activities/deviations target/actual

 

Material analysis - inspection lots