Relative Target/Actual Schedule Deviation  Locate the document in its SAP Library structure

Technical Name: 0C_RELSCHDEV

Use

Planned/Actual Comparison - Operation/Work Center View: This InfoObject calculates the average, relative target/actual schedule deviation per operation in the work center.

The relative target/actual schedule deviation is made up of the difference in time between the target/actual schedule deviation of the end of an operation, minus the target/actual schedule deviation of the start of an operation.

The relative schedule deviation describes how much a work center has contributed to the delay or acceleration of an order run. A minus sign shows that the work center has delayed the production cycle.

Example

Schedule deviation, operation finish: -2 days, that is to say the target finish was exceeded by 2 days.

Schedule deviation, operation start: -1 day, that is to say, the target start was exceeded by 1 day.

Relative schedule deviation = -2 – (-1) = - 1 Day

Technical Data

Available from Release

R/3 Release 3:0F

Calculation

Rel.T/A Sch.Dev.’ / 'Num.ProdOrd.'

 

 

 