Relative Target/Actual Schedule Deviation
Technical Name: 0C_RELSCHDEV
Use
Planned/Actual Comparison - Operation/Work Center View:
This InfoObject calculates the average, relative target/actual schedule deviation per operation in the work center.The relative target/actual schedule deviation is made up of the difference in time between the target/actual schedule deviation of the end of an operation, minus the target/actual schedule deviation of the start of an operation.
The relative schedule deviation describes how much a work center has contributed to the delay or acceleration of an order run. A minus sign shows that the work center has delayed the production cycle.
Example
Schedule deviation, operation finish: -2 days, that is to say the target finish was exceeded by 2 days.
Schedule deviation, operation start: -1 day, that is to say, the target start was exceeded by 1 day.
Relative schedule deviation = -2 – (-1) = - 1 Day
Technical Data
|
Available from Release |
R/3 Release 3:0F |
|
Calculation |
‘ Rel.T/A Sch.Dev.’ / 'Num.ProdOrd.' |