Function documentationProject Status Summary Workbench Locate this document in the navigation structure

 

The Project Status Summary channel shows the current status of each of your projects. Status indicators are as follows:

  • Future: All milestone dates are in the future.

  • Green: Project activity has begun and all dates are on target.

  • Yellow: Some tasks did not start on their planned start date, or have projected end dates that are later than the baseline end date.

  • Red: The projected end date for the project is later than the baseline end date, indicating that the critical path is delayed.

In the Project Status Summary channel, you can do the following:

  • View the current status of all projects to which you have access

  • Link to a project

  • View a report of a project's tasks and dates

Recommendation Recommendation

SAP recommends that you ask your system administrator to do any editing in the Project Status Summary channel.