Project Cycle Time Summary by Product Category 
This report compares the length of time it takes to complete projects by category. It allows you to see the amount of activity occurring per category and to identify which categories take longer to complete.
Note
Only projects that contain a product category name are included on this report.
This report table includes a vertical bar graph comparing the actual average cycle time by product category over time. Each bar represents the actual average cycle time for all the projects with completed tasks that started in the shown month.
Field |
Description |
|---|---|
Unlabeled |
Choose the document icon in this column to display the category record. |
Category |
The product category for the project. |
Description |
The description for the product category. |
Start Month |
The month and year that contains projects that were launched in the given month and have completed tasks. |
Completed Projects Launched |
The number of projects with completed tasks that were started in the month shown. |
Actual Avg Cycle Time (Days) |
The average cycle time of the projects in this category based on actual dates. |
Baseline Avg Cycle Time (Days) |
The average cycle time of the projects in this category based on baseline dates. |
This report table provides details about each of the projects in the categories shown in the summary section. A link lets you view schedule task details in each project.
Field |
Description |
Name |
The project name. You can choose the project name link if you have access to this project. |
Summary Category |
The parent category name. |
Category |
The product category name. |
Baseline Start |
The Baseline Start Date of the earliest schedule task or milestone on the project schedule. |
Baseline End |
The Baseline End Date of the latest schedule task or milestone on the project schedule. |
Baseline Cycle Time (Days) |
The number of days between the Baseline Start Date and Baseline End Date. |
Actual Start |
The Actual Start Date of the earliest schedule task or milestone on the project schedule. |
Actual End |
The Actual End Date of the latest schedule task or milestone on the project schedule. . |
Actual Cycle Time (Days) |
The number of days between the actual Start Date and Actual End Date. |
Variance |
The percentage variance of actual against baseline. Variance = (Baseline Cycle Days - Actual Cycle Days)/Baseline Cycle Days |