Function documentationProject Status Summary Locate this document in the navigation structure

 

This report provides visibility into the current status of your projects, including the ability to drill down to project schedule details when necessary to review late or high-risk projects.

Project Summary Status

This report table lists your projects with high-level status information. This report only displays projects for which you are the owner or a collaborator.

Field

Description

ID

Choose the document icon in this column to display the project document.

Project

The project name.

Description

The project description.

Owner

The project owner.

Status

Choose the status link to see the Project Status Detail.

Complete: All schedule events have an Actual End Date.

Late: One or more schedule events is overdue.

Future: All schedule events have Planned dates that are later than the current date.

Manager's Status

The risk indicator for the project.

Project Status Detail

This report table lists each schedule task and milestone event with planned and current dates and status information.

Field

Description

Milestone

The name of the milestone or task event.

Assigned

The assigned owner of the schedule event.

Original End

The Baseline End date of the schedule event.

Plan/Act Start

The Planned Start date (if the schedule event is not active) or the Actual Start date (if the schedule event has had activity).

Plan/Act End

The Planned End date (if the schedule event is not done) and the Actual End date (if the schedule event is complete).

Active

Displays X if the event has an Actual Start date entered, but no Actual End date.

Done

Displays X if the event has an Actual End date entered.

Late

Displays X if the event is complete, but the Actual End date is later than the Original End date or if the current date is later than the Original End date and the event is not complete.