Master Agreement Schedule Tracking and Schedule Dependents 
On the Tracking tab, you can review date information, and enter and edit the actual dates for an event
To see the Tracking tab, choose Add on the Schedule tab.
On the Dependents tab, you can view the events that are dependent on a specific event.
To see the Dependents tab, choose Add on the Schedule tab.
Field |
Description |
|---|---|
Baseline Start |
This value is based on the date you enter in the Fixed at field on either the Schedule page or the Settings tab. If the event is dependent on another event, this date is determined by the end date of the dependency. The baseline start date reflects the date you enter when creating the event. If you edit the date after event creation, and the Lock baseline dates option on the Schedule page is selected, the baseline date on the Tracking page remains the same, while the planned dates change. Once an actual start or end date is entered for any event in the project, the baseline dates are locked automatically. |
Baseline End |
The baseline end date for a task is determined by the baseline start date (in the Fixed at field on the Schedule page), or by the dependency end date, plus the value in the Duration field. Once an actual start or end date is entered for any event in the project, the baseline dates are locked automatically. |
Planned Start |
This value is based on the date you enter in the Fixed at field on either the Schedule page or the Settings tab. If the event is dependent on another event, this date is determined by the end date of the dependency. The planned start date is identical to the baseline start date, unless the baseline dates are locked. You lock the baseline dates by checking the Lock baseline dates box on the Schedule page or by entering an actual start or end date for any event in the project. If baseline dates are locked, and you edit the dates on the Schedule page, the planned date values on the Tracking page will change, while the baseline date values remain the same. |
Planned End |
The planned end date for a task is determined by the planned start date (in the Fixed at field on the Schedule page), or by the dependency end date, plus the value in the Duration field. The planned end date is identical to the baseline end date, unless the baseline dates are locked. You lock the baseline dates by checking the Lock baseline dates box on the Schedule page or by entering an actual start or end date for any event in the project. If baseline dates are locked, and you edit the dates on the Schedule page, the planned date values on the Tracking page will change, while the baseline date values remain the same. |
Actual Start |
You enter the actual start date after a task is started or a milestone is accomplished. Entering the actual start date for an event is crucial to project schedule tracking. Once an actual start or end date is entered for any event in the project, the baseline dates are locked automatically. |
Actual End |
You enter the actual end date after a task is finished or a milestone is accomplished. Entering the actual end date for an event is crucial to project schedule tracking. |