Function documentationTest Evaluation Locate this document in the navigation structure

 

This view contains an overview of all test plans and the status of the corresponding test cases. To evaluate the test plans in more detail, various tools are available.

Prerequisites

To be able to use the BI reports, you must meet the following requirements:

  • You have the necessary authorizations for BI reporting and the Test Workbench. For more information, see the SAP Solution Manager security guide on SAP Service Marketplace, under   http://service.sap.com/instguides   SAP Components  .

  • You have configured a BI system. For more information, see the Customizing for SAP Solution Manager under   SAP Solution Manager   Basic Settings  .

  • You have made the BI reporting settings. If you have created your own message priorities or test case status definitions in SAP Solution Manager, you have assigned these to the corresponding BI priorities and BI status values. For more information, see the Customizing for SAP Solution Manager under   SAP Solution Manager   Scenario-Specific Settings  .

  • You have assigned your Test Workbench objects to a release status schema in which the required status information is marked as BI-relevant. For more information, see Assigning Release Status Schemas to Test Workbench Objects.

Features

The following tools are available for a more detailed evaluation of test plans:

  • Status information system (for selected templates or test plans)

  • BI reporting (for selected templates, test plans, or test series)

  • Status overview

  • Message overview

Predefined Filters

For the status information system and BI reporting, you can open the reports with various predefined filters. The filters are always based on the values of one or more selected rows. The following filters are available:

  • For selected templates: The template indicates whether you are dealing with a project, solution, or test catalog. All test plans that belong to one of the selected templates are taken into account in the report.

  • For selected test plans: Only selected test plans are evaluated. You can select several test plans at once.

  • For selected test series: All test plans that belong to the selected test series are evaluated.

BI Reporting

You can use BI reporting to graphically display various reports. You can use the following reports:

  • Status Report: Overview of the status of test cases at a certain time

  • Progress Report: Overview of the progress of the test case status information over a certain period

  • Message Report: Overview of the number and status of messages at a certain time

  • Message Report by Priority: Overview of the number and priority of messages at a certain time