This graphic is explained in the accompanying text Scheduling Dependent Operations According to the Scheduling Mode  Locate the document in its SAP Library structure

The following graphic shows an example for the rescheduling of an operation using the insert operation scheduling mode and the scheduling dependent operations according to the scheduling mode scheduling submode. You have defined that the system should maintain time relationships.

 

This graphic is explained in the accompanying text

 

You reschedule operation A10 to another date. Operation A10 is the selected operation, and resource 1 is therefore the selected resource. The system must shift operation B10 on the selected resource to a date in the future so that operation A10 can be scheduled on the new desired date. A10 and B10 have time relationships to further dependent operations on dependent resources 2 and 3. The system also reschedules these dependent operations with the insert operation scheduling mode in order that the relationships can be observed.

 

 