Use
In Production Planning and Detailed Scheduling, if you want to protect an activity or the primary resource, on which the activity is processed, from unforeseen delays in material staging, you can schedule using a resource-specific time buffer. The time buffer represents a type of safety time: Using the time buffer, the system keeps a larger time interval between the activity and its predecessor activities during scheduling. Possible delays in the predecessor activities can be caught by the time buffer and a standstill in resources due to material shortage can thereby be avoided. Here, predecessor activities are the activities that have a time relationship or a
pegging relationship to the activity. When scheduling with time buffers, the system must – depending on the type of relationship – keep the following minimum time intervals between the activities:

If you do not specify a minimum interval in the PPM for a relationship, the system uses 0 as the minimum interval; during scheduling with time buffers, the minimum interval is therefore the duration of the time buffer.
In the PPM you can specify for each relationship if the system can use the time buffer during scheduling.
Scheduling with time buffers is not relevant to activities of orders that are based on an iPPE plan.
Prerequisites
General Prerequisites
Specific Prerequisites for Scheduling with Time Buffers in Time Relationships

Note that it often does not make sense to have a time buffer between the setup activity and the processing activity of an operation.
Specific Prerequisites for Scheduling with Time Buffers in Pegging Relationships