Start of Content Area

This graphic is explained in the accompanying text Displaying the Fill Level  Locate the document in its SAP Library structure

Use

In the detailed scheduling planning board, you can display and hide charts with fill level curves that represent the fill level over time for container resources.

The minimum production quantity specified in the master data for the resource and the maximum stock level are displayed in the diagram section by a red line. By double-clicking on the fill level curve, you can display a complete list of all operations that fill or empty the container resource and you can navigate further from there.

Prerequisites

You have defined a fill level chart in Customizing for the DS planning board.

For more information, see the Implementation Guide for the DS Planning Board under Maintain planning board profiles.

Procedure

Displaying the fill level chart

  1. Select the required resources.
  2. Choose Extras Fill level

Hiding the fill level chart

Choose Extras Fill level Hide chart

 

 

End of Content Area