Use
In the
detailed scheduling planning board, you can display and hide charts with fill level curves that represent the fill level over time for container resources.The minimum production quantity specified in the master data for the resource and the maximum stock level are displayed in the diagram section by a red line. By double-clicking on the fill level curve, you can display a complete list of all operations that fill or empty the container resource and you can navigate further from there.
Prerequisites
You have defined a
fill level chart in Customizing for the DS planning board.For more information, see the Implementation Guide for the DS Planning Board under Maintain planning board profiles.
Procedure
Displaying the fill level chart
Hiding the fill level chart
Choose Extras → Fill level → Hide chart